Ming RenBroker · RE/MAX Realtron Realty Inc., Brokerage
☎ 647-779-9186

Pre-Construction & New Homes

You Paid Six Figures in Pre-Construction Deposits. How Much Is Actually Protected?

By , Broker, RE/MAX Realtron Realty Inc. (About Ming) · Published

Ming Ren · Broker · RE/MAX Realtron Realty Inc., Brokerage

← All articles · Pre-Construction & New Homes · Category guide

I am Ming Ren, a Broker with RE/MAX Realtron.

The plain conclusion first: pre-construction deposits in Ontario are protected, but the protection has hard caps, and condos and freehold homes run under two different systems. The most dangerous assumption a buyer can make is "whatever I paid, Tarion covers." This article covers three things: how the money goes out, where it sits after you pay it, and how much you would actually get back if the builder failed.

First: deposits are paid in stages — copy the schedule into your calendar

A resale purchase usually involves one deposit. Pre-construction is different: deposits are paid in instalments under the schedule in your Agreement of Purchase and Sale — a payment on signing, then further payments at set intervals or milestones, building to an agreed total by occupancy. The schedule is a contract term, not a legislated standard, and it differs from project to project.

What I tell clients to focus on is not the headline percentage. It is each instalment's exact date and amount. A pre-construction purchase can run for years between signing and delivery. Miss one instalment and you are in default — the money already paid and your rights under the contract are both at risk. On the day you sign, transfer the whole schedule into your calendar and start arranging each payment well ahead of its due date.

Second: where the money sits matters more than who you paid it to

Condominiums. Under the Condominium Act, 1998, deposits on a new condo unit must be held in trust by a trustee (typically the builder's lawyer) — the builder cannot simply spend them. That is the first layer of protection, and it comes from the statute itself. Tarion adds a second layer: if deposits are not handled as required, or a builder fails to refund money that is owed, Tarion's deposit protection for a condo unit is capped at $20,000, plus limited interest (confirm the current figure at tarion.com).

The obvious problem: condo deposits usually total far more than $20,000. The excess is protected a different way — through Excess Condominium Deposit Insurance (ECDI). If a builder wants to use deposits above the protected amount toward construction before the condominium is registered, it must first obtain ECDI coverage, held through the trustee. So at signing, have your lawyer confirm two things: does this project carry ECDI, and does the coverage extend to the full amount you will have paid in?

Freehold homes. Freehold deposits are generally not subject to the same mandatory trust structure, so the risk exposure is larger — and Tarion's direct protection is correspondingly higher. Under Tarion's published rules for agreements signed on or after January 1, 2018: homes priced at $600,000 or less are protected up to $60,000; homes priced above $600,000 are protected at 10% of the price, to a maximum of $100,000. Older agreements fall under different limits, so the signing date matters.

One newer procedural point for freehold buyers: recent rule changes require new freehold buyers to notify Tarion of the purchase within a set window after signing (currently 45 days), and whether that step was completed can affect the protection available. Condo buyers are not affected by this requirement. Have your lawyer confirm the current rule and make sure the step gets done, with a receipt kept on file.

Third: if the project is cancelled or the builder fails, what do you actually recover?

Run the worst case before you need it. If a builder cancels a project, defaults, or becomes insolvent, your deposits are in principle refundable. Whether you recover in full, and how quickly, depends on three things: whether the money is still in trust, whether there is adequate ECDI (for condos), and where Tarion's cap sits relative to what you paid.

An illustrative example with numbers I made up: suppose you paid $120,000 in deposits on a condo unit. If the money stayed in trust and the project carries full ECDI coverage, your position is comparatively strong. If instead the money was not properly held and ECDI coverage fell short, Tarion's own backstop only reaches its cap — the rest would leave you standing in line as a creditor in an insolvency, which typically means a long wait and partial recovery. Same $120,000 paid; radically different outcomes depending on how the money was held.

This is why I insist clients look past the floor plan and the price list. Before paying a deposit, check the builder: Is it registered and in good standing with Tarion? What is its licensing status with the Home Construction Regulatory Authority (HCRA)? What does its delivery record on past projects look like?

For contrast, a resale deposit is paid to the listing brokerage's regulated real estate trust account, is usually a single payment, and is only at risk for weeks or months. Pre-construction deposits are larger, are outstanding for years, and are protected only up to defined limits — the due diligence should match that difference.

Three common misunderstandings

Misunderstanding 1: "Tarion protects all of my deposit." It does not. Tarion's direct deposit protection is capped — $20,000 for a condo unit, and for freehold, $60,000 or 10% of the price up to $100,000 depending on price (confirm current figures at tarion.com). Amounts above the cap rely on trust arrangements and ECDI, not on Tarion.

Misunderstanding 2: "The money is in trust, so it is 100% safe." Trust is an important layer, but confirm who the trustee is and what the contract actually says — and for a condo, confirm the ECDI exists and is large enough. "I heard it's in trust" is not the same as having verified it.

Misunderstanding 3: "The deposit schedule is the builder's paperwork — a few days late won't matter." The schedule is a contract obligation. A late instalment is a default, and the builder may have the right to terminate and pursue the deposits already paid. If a payment problem is coming, raise it early and in writing; do not quietly drift past the date.

Before you sign and pay, do these in order

  1. Copy every line of the APS deposit schedule into your calendar — date, amount, payee — and plan the funding for each instalment in advance.
  2. Have your lawyer confirm who holds the deposits in trust and under what account terms; for a condo, confirm whether ECDI is in place and for how much.
  3. Calculate your own Tarion protection line before you pay: condo buyers, compare the $20,000 cap against your total deposits; freehold buyers, apply the $60,000 / 10%-to-$100,000 tiers to your price.
  4. Freehold buyers: confirm who is responsible for the Tarion notification step within 45 days of signing, and keep the confirmation.
  5. Check the builder before the first cheque: Tarion registration status, HCRA licence, and delivery history on earlier projects.
  6. Keep a dedicated file — cheque copies, receipts, bank records — for every deposit, and keep it until after final closing.

— Ming Ren, Broker, RE/MAX Realtron


This article is general information, not legal advice and not an official Tarion interpretation. Your deposit schedule, trust arrangements and ECDI terms will affect the outcome; consult an Ontario lawyer and confirm details with Tarion before acting.

Primary sources: Tarion Warranty Corporation (tarion.com), Deposit Protection; Condominium Act, 1998 (Ontario e-Laws) trust requirements for condo purchase money; Ontario New Home Warranties Plan Act (reviewed November 2026). The $120,000 deposit is an illustrative figure, not a real case; $20,000 / $60,000 / $100,000 are Tarion's published protection caps — confirm the current amounts at tarion.com when signing.

This article in other languages: 中文فارسی

Want to talk about your home?