The plain conclusion first: a backyard project has to pass two gates, and they are not the same gate. The first is the provincial building permit system — whether the structure must be reviewed and permitted before you build. The second is your municipality's zoning by-law — where on the lot it may sit, how tall and how large it may be, and how far it must stay from the lot lines. Passing the first gate, or being exempt from it, does not waive a single zoning rule. Toronto's own permit page says it plainly: even if a building permit is not required, compliance with the Zoning Bylaw is required. This article uses the Ontario Building Code and Toronto's published lists as the worked example; outside Toronto, your own city's by-law and building department give the numbers that govern you.
1. A shed's exemption is a five-condition list — all five, at once
Under the current Ontario Building Code (the 2024 Building Code, O. Reg. 163/24), Division C, a shed is exempt from the permit requirement and from the Code itself only if it meets all of the following:
| Condition | Requirement |
|---|---|
| Size | Not more than 15 m² in gross area (about 161 sq ft) |
| Height | Not more than one storey |
| Attachment | Not attached to a building or any other structure |
| Use | Used only for storage purposes ancillary to a principal building on the lot |
| Plumbing | No plumbing |
The conditions are cumulative, not a menu. Miss one and you are back under the general rule: a permit is required and the Code applies. The failures I see are predictable — a shed built tight against the house (attached), a tap roughed in for convenience (plumbing), or a "shed" that is really a studio or a bunkie (a different use). One boundary point deserves care: the Code's wording is "not more than 15 m²," while Toronto's permit page lists a shed of 15 m² or more on its "permit required" side. The two published wordings do not line up perfectly at exactly 15 m². If your shed lands exactly on that line, ask your building department before you buy the kit — or choose the next size down.
2. Decks have no matching Code exemption — the city draws the line
A deck is not a shed with a different name, and it has no equivalent exemption in the Code list. In practice the line is drawn by each municipality's published permit list. In Toronto, the city's page lists a deck more than 60 cm (24 inches) above ground as work that requires a building permit, and enclosing an existing deck, porch or balcony requires one at any size.
On the no-permit side, Toronto lists an uncovered platform only where its finished deck level is not more than 60 cm above the adjacent finished grade, it does not form part of an exit required under the Building Code, and it complies with the Zoning Bylaw. Three details are easy to miss. First, the exemption is written for an uncovered platform — plan a roof or enclosure, now or later, and you are outside it. Second, if the deck forms part of a required exit route from a door, the exemption does not apply. Third, other municipalities draw this line differently — some look at attached decks or larger decks as well — so confirm against your own city's page before you build.
3. Zoning controls location, height and coverage — permit or no permit
Nobody reviews zoning for a permit-exempt project, because nobody reviews anything. The rules still apply, and a structure built in the wrong place can be ordered corrected or removed. In Toronto's residential zones, the zoning by-law regulates ancillary buildings and structures as a class: among other things, they may not be located in a front yard, and the by-law sets setbacks from lot lines and the main building, height limits, and caps on combined ancillary area and lot coverage. The exact numbers turn on your zone and your lot, so this article deliberately gives no single set of figures as a universal answer. The right move is to check the applicable chapter for your address, or ask the city for a zoning review, and keep the answer in writing.
There is also a resale consequence worth knowing now rather than later: a deck or shed built without a required permit, or in breach of zoning, can surface in a buyer's lawyer's title and compliance inquiries when you sell. "Nobody complained while I lived there" is not the same as "nobody will ask at closing." If a sale is anywhere on your horizon, keep the paper.
Three misunderstandings I hear most often
"No permit needed means I can build it however I like." No. What is waived is the permit, not the zoning. Location, height, setbacks and coverage all still apply — and with no plans review, the responsibility for getting them right sits entirely with the owner.
"A shed is fine as long as it is under 15 m²." Size is one condition of five. Attachment, plumbing, a second storey, or a change to living or working use each independently end the exemption.
"My neighbour's deck has no permit and nothing happened." Non-enforcement is not permission. Work built without a required permit can lead to a permit after the fact, additional fees, and in serious cases alteration or removal — and the problem travels with the property when it is sold.
If you are planning backyard work this year, do these in order
- Describe the project precisely first: shed or deck, dimensions, height above grade, attached or free-standing, roofed or open, any plumbing. Those answers decide which rules you are under.
- Test it against the Code's five conditions and your city's permit list. If a measurement sits exactly on a boundary line, get the building department's answer before buying materials.
- Then test zoning: location, setbacks, height and coverage against your municipal by-law, and where anything is unclear, request the city's answer in writing.
- If a permit is required, get it before work starts, complete the required inspections, and keep the permit and inspection records on file.
- If you may sell, file the permit, drawings and any city correspondence with your house documents, so closing questions can be answered with paper instead of memory.
Trust Professional, Diligent Work. I am Ming Ren. Before the backyard work starts, clear both gates and we will go through the city's written answers, item by item.
This article is general information only, not legal or construction advice. Zoning by-laws and permit lists differ by municipality; confirm with your local building department before starting work.
Primary sources: Ontario Building Code (O. Reg. 163/24), Division C, 1.3.1.1.(6); City of Toronto, "When do I need a building permit?" (toronto.ca, consulted November 2026); Toronto Zoning By-law 569-2013 framework for ancillary buildings and structures. No figures from any real property are used.