The plain conclusion first: a standby generator is not "buy a machine and wire it in." In Ontario, a standby power system that can discharge contaminants into the air takes one of two environmental routes. If it meets the eligibility rules, it is registered on the EASR — the Environmental Activity and Sector Registry — a standardized online filing. If it does not, it needs an Environmental Compliance Approval (ECA), a full ministry review in a different league of time and paperwork. Which route applies is set by the system's own characteristics — size, fuel, purpose and the regulation's criteria — not by what the owner or tenant prefers. Settle the route before work starts, then settle who pays, who registers and who maintains. Reverse that order and you can end up with an installed machine that cannot be registered, which is the weakest position of all.

1. The dividing line is written in the regulation

Part II.2 of Ontario's Environmental Protection Act created the EASR: for standardized, routine activities, instead of individual approvals, the person engaging in the activity registers it and operates under prescribed conditions. O. Reg. 245/11 lists the activities that may be registered, and its Part IV deals specifically with standby power systems: using, operating, constructing, altering, extending or replacing a qualifying standby power system is a prescribed activity under that regulation.

Three points hold the logic together:

  • Registration is not an exemption; it is a different kind of approval. The registrant files information about the activity, the site and the contact person in the registry, certified as complete and accurate by a person with authority to do so. From then on, the system must be operated in continuing compliance with the regulation's activity requirements. A system that cannot meet the conditions does not belong in this channel at all.
  • What cannot use the EASR goes to an ECA. A system whose scale, configuration or purpose falls outside Part IV's eligibility scope follows the general approval path under the Environmental Protection Act and is reviewed by the ministry. When a tenant or vendor says "it's just a registration," a landlord should ask for the basis of that eligibility conclusion — their own reading of the regulation, or an environmental consultant's opinion.
  • Registration is a continuing state, not a filing cabinet. Filed information must be updated when it changes, and replacements, expansions and transfers all require the registration to be revisited. On a purchase of the property, whether a generator registered by a predecessor is complete and has been operated in compliance is a due-diligence item.

2. Whoever "engages in the activity" registers — so the lease must say who that is

The EASR duty sits on the person engaging in the activity. In a commercial building that person may be the landlord, or may be the tenant who paid for the machine and runs it — it turns on whom the generator serves and who controls its operation:

Situation Who ordinarily registers What the lease must settle
Building standby power serving the whole property The landlord How operating and maintenance costs are shared with tenants; what gets priority on an outage
One tenant's own generator (data, cold storage, medical) The tenant Tenant registers and maintains the filing; at exit, removal or leaving the unit in place, and how the registration is closed out
Landlord-installed, dedicated to one tenant The party who actually controls operation — determined on facts, not guessed Who registers, who maintains, who bears non-compliance, in writing

The classic failure is each side assuming the other filed. My practice is to write the registration duty straight into the lease: which party completes the registration (or obtains the ECA) before work begins, delivery of the registration confirmation to the other side, who keeps the operating conditions met and the filing updated, and who bears the consequences of a breach. An environmental officer will look at who is engaging in the activity; the lease allocates the account between you afterwards.

3. Beyond the environmental filing: fuel, electrical and building are three more files

The EASR answers only the emissions question. A diesel or gas generator in a commercial building also sits inside several other rule sets, each to be verified before signing and before work:

  • Fuel storage: diesel tanks and gas supply engage the fuel safety rules administered by the TSSA (Technical Standards and Safety Authority) — tank capacity, containment and ventilation all carry specific requirements, with licensed persons designing and installing.
  • Electrical connection: the tie-in to the building's distribution and the transfer switch must meet the electrical code, installed by licensed electricians and inspected by the ESA (Electrical Safety Authority).
  • Building and fire: the generator room's location, exhaust, noise, structural load and building permit follow the municipal building department and fire requirements; noise also engages nearby sensitive uses and the local noise by-law.

The common thread: licensed professionals and advance confirmation in every file, nothing left to be patched after the machine arrives. Making "all registrations and approvals in hand" a precondition to starting work protects both sides.

Three misunderstandings I hear most often

"A standby generator only runs during outages, so there is nothing to file." Standby power systems are precisely one of the activities O. Reg. 245/11 names. Test runs and scheduled loaded exercises discharge too; whether registration applies turns on the activity class and the eligibility criteria, not on how few hours a year the machine runs.

"EASR registration is a web form — file it once and forget it." Registration is the beginning. The filed information must stay accurate and be updated when it changes, and the system must be operated within the activity requirements for as long as it runs. A registration nobody maintains is a non-compliant machine with your name on it.

"The tenant installed it, so the environmental responsibility is entirely the tenant's." The duty follows who engages in and controls the activity, and the property owner's position and knowledge can also come into an enforcement picture. If the lease never assigns registration and operating responsibility, neither side has anything ready to point to when something goes wrong.

If a generator project started today, do these in order

  1. Get the eligibility call in writing: an environmental consultant or the equipment supplier tests the system against Part IV of O. Reg. 245/11 and states EASR or ECA, with the reasoning kept on file.
  2. Fix the registrant: determine it from whom the generator serves and who operates it, write it into the lease or the work agreement, and have both sides keep the registration confirmation.
  3. Verify the fuel (TSSA), electrical (ESA), and building and fire files in parallel, and make all of them preconditions to starting work.
  4. Set the operating arrangements: test-run frequency and hours, maintenance records, and who owns updates to the registration.
  5. Set the endgame: at lease end or on a sale of the property, removal or leaving in place, who handles registration changes or closure, and who pays.

Trust Professional, Diligent Work. I am Ming Ren. If a generator is going into your building, bring the eligibility assessment and the registration plan first, and we will go through the regulation item by item.


This article is general information only, not legal or environmental compliance advice. The eligibility criteria and activity requirements in O. Reg. 245/11 rest on the current Ontario e-Laws text; for a specific system, consult an Ontario environmental compliance consultant and a lawyer.

Primary sources: Environmental Protection Act, R.S.O. 1990, c. E.19, Part II.2 (s.20.21 and related provisions); O. Reg. 245/11, Part IV — Standby Power Systems (Ontario e-Laws, consulted November 2026).

This article in other languages: 中文فارسی

Want to talk about your home?

You can also call directly, or scan the code to add Ming on WeChat.

Ming’s WeChat QR code
Scan to add on WeChat

Community guides by city

All cities →
☎ Call MingFree Evaluation