I am Ming Ren, a Broker with RE/MAX Realtron.
The plain conclusion first: on a self-build, a buy-the-lot-and-build, or a tear-down rebuild, the lender does not hand you the full loan on closing day. A construction mortgage runs on a simple logic — work first, inspection second, money third. Funds are released in stages, each stage is verified before it is paid, you are charged interest only on the amounts advanced so far, and only when the home is complete does the loan convert into an ordinary amortizing mortgage. The builds that run into trouble are rarely under-budgeted in total. They stall because the cash did not arrive in the order the work demanded it.
1. First, know which of the two models you are in
Construction financing comes in two models with completely different cash-flow shapes, and you need to know which one you signed:
- The draw model (progress-draw mortgage): the lender releases funds in stages as the build reaches milestones, inspecting the work before each advance. Custom builds, tear-down rebuilds and projects with smaller builders almost always use this model. It is the one this article is mainly about.
- The completion model: the mortgage is arranged up front but funds only on possession. The builder carries the construction costs, and you pay no interest during the build. Large production builders commonly use this model, and for the buyer it feels much like a regular mortgage.
Both are called construction mortgages, which is where the confusion starts: one requires you to float cash through the entire build, the other barely at all. When someone tells you their construction loan was simple, ask which model it was before you draw conclusions for your own project.
2. The rhythm of a draw mortgage: inspect, advance, repeat
There is no province-wide draw schedule. The stages and percentages in your own lender's commitment govern. The common shape runs from a land advance, then through stages such as foundation complete, lock-up (framing, roof, doors and windows in, the building weather-tight), mechanical systems and exterior, and finally full completion. As one published example, a major bank's self-build program offers an initial land draw of up to about 65% of the appraised lot value — which means a substantial share of the land cost comes out of your own pocket first, and that figure is one lender's practice, not a rule. Your commitment letter is the only version that counts.
Every draw runs the same cycle: the builder completes a stage; you submit the draw request and supporting documents; the lender sends an appraiser or inspector to confirm the work is actually done to that stage and the value supports the advance; then the funds are released. Two consequences follow. First, money always trails the work by half a step, so where the builder's payment schedule and the lender's draw schedule do not line up, your own cash bridges the gap. Second, the lender's inspection verifies progress and value for lending purposes — it is not a quality inspection. Municipal building inspections are a separate system, and neither substitutes for the other.
On interest: during construction you generally pay interest only on the balance advanced so far. Early draws are small, so early interest is small; the balance, and the monthly interest, grow as the build proceeds. Once the home is complete and the final inspection passes, the loan converts to a regular amortizing mortgage and the rate and amortization you negotiated take over from there. Which means the length of the build is itself a cost: every extra month is another month of construction-period interest, and a long delay can run into the expiry of the lender's commitment.
3. One slice of every payment does not reach your builder right away
This is the layer first-time self-builders most often miss in Ontario: section 22 of Ontario's Construction Act requires the payer to retain a basic holdback of 10% of the price of the services and materials supplied, held against construction lien claims. The current lien preservation period is 60 days.
In cash-flow terms: even when the lender approves a draw, 10% of the value of the work is held back as that money flows to the builder, and it is released only after the applicable period runs and the release conditions are met. Experienced builders price this into their contracts. First-time builders tend to budget as if the approved draw equals the payable amount, and then find every stage slightly short. Keep two things separate in your mind: the statutory holdback is a legal retention; a lender advancing less, or later, because its inspection supports less progress is a different mechanism — and both can apply to the same draw.
There is also an order-of-money point. Lenders commonly expect the borrower's own equity to go in first. Design fees, permits, deposits and the equity portion of the land — the soft costs of the project — are usually spent before the first draw arrives. A self-build cash plan has to be sequenced as "my money first, the lender's money reimbursing behind it," not the other way around.
Three misunderstandings I hear most often
"The loan was approved for this amount, so that amount is available to spend." No. What is approved is a total facility. What you can use arrives in stages, each gated by completed work, an inspection, and the holdback. If one stage stalls, later money does not move forward to rescue it.
"The lender's inspector passed the stage, so the workmanship must be fine." No. The lender's inspection confirms progress and value to support an advance. Workmanship is covered by municipal inspections, your contract, and whatever supervision you arrange yourself. Treating a draw inspection as a quality sign-off is an expensive misunderstanding on a build.
"Payments are low during construction, so this phase is cheap." Construction-period payments are interest-only on a growing balance, so they look low early on — before the full interest cost has arrived. A longer build means more interest, plus variables like commitment expiry and renewal fees. The money "saved" by a slow build is often smaller than the extra interest it creates.
Do these five things, in order
- Confirm the model before you sign: progress draws or completion funding. Read your lender's commitment for the draw stages, the conditions on each advance, and the commitment's expiry date.
- Lay the builder's payment schedule beside the lender's draw schedule and compare them line by line. Where they do not match, arrange your bridging cash in advance.
- Give your budget three separate lines: upfront equity (design, permits, deposits), the cash tied up by the 10% holdback at each stage, and construction-period interest estimated on the longest realistic build time, not the planned one.
- Start each draw early: book the inspection and assemble invoices and progress documents before the builder's invoice lands. The draw cycle belongs in the construction schedule.
- Have your real estate or construction lawyer review the holdback release, lien periods and the payment terms of the building contract. If the build may run past a year, confirm the commitment expiry and renewal arrangements in writing.
Trust Professional, Diligent Work. I am Ming Ren. On a self-build, the hard part of the arithmetic is not the total — it is the order. If you have a build or a purchase in front of you, bring the lender's commitment and the building contract and we will go through the numbers and the paperwork, item by item.
This article is general information only, not legal or financial advice. Draw stages, percentages and conditions are set by each lender's written commitment; holdback and lien rules follow the current text of Ontario's Construction Act. Consult your lender and an Ontario lawyer before acting.
Primary sources: Ontario Construction Act, s.22 (10% basic holdback) and lien-period rules (Ontario e-Laws); CMHC and major-lender published construction (progress-draw) mortgage guidance (consulted November 2026). The 65% land-draw figure is one lender's published example, not a province-wide standard.