Leasing Hydro Corridor Land in Ontario: Whose Land It Is, and Who Approves First

By , Broker, RE/MAX Realtron Realty Inc. (About Ming) · Published

Ming Ren · Broker · RE/MAX Realtron Realty Inc., Brokerage

← All articles · Commercial Real Estate & Leasing · Category guide

I'm Ming Ren, a Broker with RE/MAX Realtron.

The plain conclusion: that open land under the transmission lines is not simply 'available.' Whether you can use it, from whom, and where you stand in line all turn on one prior question — is this provincial corridor land, or private land crossed by a Hydro One easement? Two kinds of land, two completely different conversations.

First: identify which kind of corridor land you are looking at

The background: in 2002 the Reliable Energy and Consumer Protection Act amended the Electricity Act and transferred the land Hydro One owned for its transmission system — roughly 50,000 acres, about 22% of its transmission grid — to the Government of Ontario. Hydro One kept the primary right to use the corridors for transmission and distribution through a statutory easement, and the towers and structures remain its property. This provincial land is managed jointly by Infrastructure Ontario (IO) and Hydro One under the Provincial Secondary Land Use Program (PSLUP).

The rest of the grid crosses private land Hydro One never owned; it holds only an easement there, and that land is not in the program. If you own such a parcel, your dealing is with the easement document. If you want to use someone else's, IO is not your counterparty. Title and easement review comes first.

Second: two gates, and the transmission gate opens first

For provincial corridor land the process is a relay. Public bodies and private parties alike may propose a secondary use. Hydro One completes a technical clearance review — compatibility with transmission on technical, operational and safety grounds. Only if Hydro One clears the proposal does IO execute the actual agreement, typically a licence or an easement.

One principle sits behind the sequence and is not negotiable: transmission and distribution are the primary use of the land. Hydro One's existing and future requirements must be met before any secondary use is considered. A commercially sensible proposal still yields to a future line or access requirement — build that priority into your expectations, because no lease term outranks it.

Third: private uses stand last in the queue

Once transmission needs are met, the PSLUP ranks secondary uses expressly: new linear public uses come first; provincial or inter-regional linear public uses outrank local ones; non-linear public infrastructure outranks private uses; public recreation also sits ahead of private uses; and multi-use corridors are preferred. Private uses — IO's own examples include pipelines, parking lots, open storage and agriculture — are permitted, including on an interim basis, but they are the last category reached.

Two practical consequences follow. A private application can wait a long time and may receive only an interim arrangement that yields to a later public use, so heavy capital spending should be tested against that uncertainty. An invented example: for open storage on corridor land, price the fencing and surfacing on the assumption the licence may not renew. And file a complete proposal — use, footprint, distances from Hydro One assets, access — because the technical review can only clear what it can see.

Three common misunderstandings

Myth 1: "The corridor is empty — just lease it from the city." Provincial corridor land is administered by IO and Hydro One under the PSLUP, with Hydro One's technical clearance first. Private corridor land is outside the program entirely.

Myth 2: "A long-term agreement makes the use secure." Agreements are typically licences or easements, and transmission remains the primary use. A secondary use yielding to transmission needs is the design of the system, not a breach.

Myth 3: "Private uses are not allowed, so applying is pointless." Last in priority is not prohibited. Parking, open storage and agriculture are IO's own examples of permitted private uses — subject to the queue, and possibly on an interim basis.

If this landed on your desk today, work through it in this order

  1. Search title first: provincial corridor land under the PSLUP, or private land with a Hydro One easement — do not mix the two routes.
  2. For provincial land, follow the sequence: Hydro One technical clearance, then an IO agreement (licence or easement), and allow time for both.
  3. File a complete proposal: use, footprint, distances from transmission assets and access, to shorten the technical review.
  4. Discount private-use economics for queue position and possible interim status; defer heavy capital spending.
  5. Confirm the agreement form, term, renewal and what happens if transmission needs end the use.
  6. For private land, go back to the easement document itself and check its limits on owner and third-party use.

I'm Ming Ren. If you are facing a commercial real estate question like this one, bring the documents first — we will go through them clause by clause, number by number.


This article is general information, not legal or tax advice. The documents, timing and facts of a specific transaction affect the answer; consult an Ontario lawyer or accountant before acting.

Primary sources: Infrastructure Ontario, Provincial Secondary Land Use Program (PSLUP) pages and FAQ; Hydro One compatible land use page (reviewed November 2026). Any specific dollar figures used as examples were invented by the author to illustrate a method and are not real transactions.

This article in other languages: 中文فارسی

Want to talk about your home?

You can also call directly, or scan the code to add Ming on WeChat.

Ming’s WeChat QR code
Scan to add on WeChat

Community guides by city

All cities →
☎ Call MingFree Evaluation