I am Ming Ren, a Broker with RE/MAX Realtron.
The conclusion first: an Ontario condo owner who wants an electric vehicle charging system at their parking spot cannot be turned away with "our rules don't allow it." Ontario Regulation 48/01 sets up a dedicated process. You deliver a proper written application; the board must respond in writing within 60 days; a rejection requires a professional report and is limited to three grounds; and if 60 days pass with no response, the board is deemed not to have rejected your application.
Owners usually stall at the management office, hearing "the building doesn't permit that" or "it needs a vote of all owners." Neither statement survives this process. Here is the sequence: how to apply, what responses are possible, and what must happen after a yes.
First: file an application that meets the requirements — the 60 days run from a compliant one
Ordinarily, an owner changing the common elements follows section 98 of the Condominium Act, 1998: board approval plus an agreement, with no fixed deadline and no list of permissible refusal grounds. EV charging was carved out. Under section 24.4 of O. Reg. 48/01, an installation carried out under sections 24.5 and 24.6 exempts both owner and corporation from section 98. And section 24.1 deems sections 24.2 to 24.7 to be part of every corporation's declaration, with no board power to amend or repeal them. So this is not a contest between house rules and the regulation — the process is already inside your building's own declaration.
Section 24.5(2) sets four requirements for the application:
- it must be in writing;
- it must identify the owner and the owner's address for service for the application;
- it must be signed by the owner; and
- it must include drawings, specifications or information about the proposed installation, including its location, that on reasonable grounds are relevant to any professional report the corporation could obtain.
The word "compliant" matters because the 60-day response clock in section 24.5(5) runs from the corporation's receipt of an application that meets subsection (2). If the board considers an application deficient, section 24.5(6) has it say so in writing, and time is spent going back and forth. Filing complete the first time is in your own interest. If you need building information or permissions to prepare the drawings, section 24.5(4) obliges the corporation to provide what is reasonably required, as soon as reasonably possible, once you ask in writing — cite it.
Second: there are only a few possible responses, and rejection has the highest bar
The board must answer in writing within 60 days, or another period agreed in writing. The possible answers:
Rejection — three grounds only, with a report attached. Section 24.5(8) says the board may reject "only if" the corporation has obtained a report or opinion from a person whose profession lends credibility to it, the report sets out its reasons, and it clearly states the installation would do one of three things: (a) contravene a law, regulation or by-law, including the Electrical Safety Code — but expressly not the corporation's own declaration, by-laws or rules; (b) adversely affect the structural integrity of the corporation's property or assets; or (c) pose a serious risk to health and safety, or a serious risk of damage to the corporation's property or assets. Under section 24.5(10), the rejection must come with a copy of that report. A letter that merely says "the board has decided not to approve" meets none of this. Note the carve-out in ground (a): your own building's rules saying "no chargers" cannot be the reason.
Not rejected, but a different manner or location required. Section 24.5(12) gives the board a middle option with two limits: the alternative must not impose unreasonable additional cost on the owner, and it must be necessary for one of two purposes — so that owners would not, on an objective basis, regard the installation as materially reducing their use and enjoyment of units, common elements or assets, or so that the installation does not contravene the declaration, by-laws, rules or an agreement of the corporation. The response must give reasons and include drawings, specifications and information; "put it somewhere else" without a plan does not comply. There is a carve-out here too: a general prohibition on charging systems in the declaration, and prohibitions or unreasonable restrictions in by-laws, rules or agreements, do not count.
Acceptance — or silence. If the board neither rejects nor requires an alternative, its response must say so. And if 60 days pass with no response at all, section 24.5(16) supplies the result: the board is deemed not to have rejected the application and not to require an alternative. Silence is not a stalling tactic here.
One cost rule for the application stage: under section 24.5(17), each side bears its own costs of the steps it takes, unless the later agreement says otherwise.
Third: a yes is not permission to start work — agreement in 90 days, effective on registration
Once the board does not reject the application (including where an alternative is required), or is deemed not to reject it, section 24.6(1) requires both sides to take all reasonable steps to sign a written agreement within 90 days, or another agreed period. The agreement's terms must be reasonable and necessary, and it must cover five things: how the installation is carried out; how installation costs are allocated between corporation and owner; each side's responsibilities, including the costs of use, operation, repair after damage, maintenance and insurance, and the costs of preparing and registering the agreement; who owns the system or any part of it; and what happens if the system is decommissioned or the agreement terminated.
There is a default rule on installation cost, which the agreement can vary: if you or your contractor installs, you bear the cost; if the corporation or its contractor installs, you bear all of the corporation's reasonable costs. In my view, this agreement is where your real attention belongs. The regulation narrows "can you install" to a few grounds, but it only requires the money questions — installation, electricity, maintenance, what happens when you sell — to be written down, not how they are answered. Read every clause before signing.
Signing is still not the end: section 24.6(5) requires the corporation to register the agreement on title to your unit, and the agreement does not take effect until it is registered. The agreement binds the unit and is enforceable against your successors — it travels with the unit when you sell, which is worth understanding before you sign, not after.
Finally, a hard deadline. Under section 24.7, disagreements under this process go to mediation and arbitration under section 132 of the Condominium Act. Section 24.7(4) provides that if neither side submits the disagreement to mediation or arbitration within six months of a rejection, or within six months after the 90-day agreement period expires without an agreement, the application is deemed abandoned and no longer valid. Sit on a rejection and half a year later you start over.
Do not confuse this with the other track: if the corporation itself installs chargers building-wide, that runs under section 24.3, exempting it from section 97, with the costs treated as common expenses and owners holding requisition rights after notice. That is a different procedure from your individual application — first establish which track your building is on.
Common misunderstandings
"The office said the building rules don't allow it, so that's the end." It is not. Building rules are excluded from the lawful rejection grounds, a rejection needs a supporting professional report, and an oral answer at the front desk is not the written response section 24.5 requires.
"All the owners have to vote on it first." An individual application under section 24.5 has no owners' meeting vote. Meetings and requisition rights belong to the corporation-installed track under section 24.3.
"The board never replied, so I have no chance." The opposite. Sixty days of silence is deemed a non-rejection with no alternative required, and you proceed to the agreement stage on your own proposal.
"Once the agreement is signed, work can start." The agreement takes effect only when registered on title to your unit. Until registration is done, it does not count.
From filing to installation, in order
- Confirm the corporation's address for service, and whether the board has passed a resolution accepting delivery by email — do not file to the wrong address.
- Have a licensed electrical contractor prepare the location, routing and specification material, and file all four application requirements complete the first time.
- If you need building information, request it in writing citing section 24.5(4), and keep proof of the delivery date; the 60 days run from receipt of a compliant application.
- If you receive a rejection, check it line by line: is the professional report attached, does it give reasons, and do the reasons fall inside the three grounds?
- If an alternative manner or location is required, check for the required drawings and reasons, and whether the added cost is reasonable.
- In the agreement, confirm all five required subjects are covered, especially who pays installation costs and the costs of preparing and registering the agreement.
- Confirm the corporation has registered the agreement on title to your unit before arranging the work.
- If there is a disagreement — a rejection, or 90 days pass with no agreement — submit it to mediation or arbitration within six months so the application is not deemed abandoned.
I am Ming Ren. If a charger is part of your plan for a condo, understand this process before you buy, and we will go through the documents one by one.
This article is general information, not legal advice. Your corporation's declaration, the agreement's terms and your own timelines can change the result. Consult an Ontario condominium lawyer before acting.
Primary sources: Ontario Regulation 48/01, ss.24.1–24.7; Condominium Act, 1998, ss.97, 98, 132 (Ontario e-Laws, checked November 2026).